Developed and submitted a Prefeasibility Study for a 66MWp PV project across 5 potential sites considering project economics, technical and regulatory aspects.

Role

Advisory

Scope

Developed and submitted a Prefeasibility Study for a 66MWp project across 5 potential sites considering project economics, technical and regulatory aspects.

Sites

Nkangala District Municipality, Mpumalanga

Energy output

Prefeasibility study indicates up to 145GWh in a phased approach with Phase 1 delivering up to 25GWh per annum

Technology review

Solar PV

Asset description

A prefeasibility study for a 66MWp PV facility intended to support three mining operations through both a behind-the-meter and wheeling arrangement

Achievements

Submitted a comprehensive Prefeasibility Study to enable the Board to make an informed decision about whether to proceed with the development of the proposed facility (decision TBC)