Platinum Co PV & BESS Project

Develop a hybrid 20 MWp solar PV + 40 MWh BESS behind-the-meter system to improve load management and grid resilience.

Role

Development / Project Oversight

Scope

Development of a hybrid 20 MW solar PV + 40 MWh BESS behind-the-meter system to improve load management and grid resilience.

Sites

Mine in North West Province

Energy output​

50 GWh+

Technology review​

Solar PV, Battery Storage

Asset description​

Hybrid PV + BESS installation

Achievements

  1. System design and sizing completed
  2. Grid connection process underway
  3. Financial modelling and EPC RFP initiated
  4. Permitting and stakeholder engagements completed
  5. Construction targeted for 2026, operations 2027
Back to all projects